|
| First
| 2 | 3
| 4 | 5
| 6 | 7
| 8 | 9
| Last |
The ISG-process
need to be flexible in order to allow for emerging issues to be discussed and
worked on.
The ISG-mechanism
will include plenary meetings, steering board, setting up an ISG-secretariat,
and thematic ad hoc groups (TAG). See 4. Below.
In the ISG-process,
ICD should be the checkpoint for national and donor activities and act as the
executive body.
3.4
Expected results and outputs
Expected direct
outputs from the project include:
1. Improved
co-ordination within MARD regarding planning and implementation of foreign-funded
projects/programmes. The evaluation of the ISG-process shows that co-ordination
between the departments of MARD and MARD-ICD is insufficient. Improved co-ordination
is a prerequisite for more efficient use of external funds. A clear co-ordination
role of ICD would minimise competition between the various departments and agencies
within MARD, and would also facilitate a broader programme approach.
2. Improved
co-ordination between MARD and other national stakeholders. There are a
large number of national agencies and research institutions connected to MARD.
Improved co-ordination between these as well as other national stakeholders
(including NGOs) involved in areas under MARD responsibilities will contribute
to greater efficiency.
3. Improved
donor co-ordination. The evaluation of the ISG noted that there were insufficient
co-operation between donor agencies, and even some competition between the agencies.
This observation was further confirmed during the workshop in September 13,
1999. Consequently, to achieve the project purpose further improvements in donor
co-ordination is necessary.
4. Improved
co-ordination between MARD and donors. A regular dialogue will contribute
to improved co-ordination between MARD and donors. The improved co-ordination
within MARD, and between donors will also lay the groundwork for a more consultative
dialogue in, for exemple, formulation of development project/programmes.
5. Functioning
information system. Currently, there is insufficient information concerning
ongoing, planned and pipeline projects/programme under the responsibility of
MARD and those related to natural resources management and rural in general.
A similar situation also exists regarding information on policies, strategies
and priorities of MARD and the donor. A database where the government and donor
institutions can get necessary information for planning and programming of their
respective development programmes, will improve the situation.
6. More
systematic learning and documentation of experiences. While almost projects/programmes
have their individual monitoring and evaluation reporting, a periodic overall
analysis of implementation performance of projects/programmes would give both
governmental agencies and donors an overview of the utilisation of external
support, and provide them with useful experiences and lessons for possible application
to future project/programmes.
7. Contribution
to policy and strategy development. The dialogue, improved co-ordination
and systematic learning will contribute to further development of policies and
strategies regarding natural resources management and rural development.
3.5
Activities
To produce
the results or outputs as defined above, a few key activities have been identified
which are outlined below. A detailed plan of activities will be worked out during
the final project preparation. Activities identified so far to be undertaken
include:
1.
Exchange experiences and policy dialogue:
a) Initiate
regular meetings with the departments and agencies within MARD.
b) Arrange
meetings with other ministries and organisations (including NGOs), and keep
planning departments in other ministries informed about ongoing activities and
planned projects/programmes.
c) Initiate
learning and policy development through:
· Identification
of a number of priority issues for policy development of special interest for
MARD and donors during a regular plenary meeting.
· Inventory
of existing policies should be carried out in relation to the identified issues.
· Establishing
thematic ad-hoc working groups (TAG) for informal exchange between MARD and
donor organisations.
· Presenting
findings from the TAG in reports and workshops
· Compiling
and disseminating information concerning experience, results and performance
evaluations of donor funded projects.
2. Pro-active
role of MARD in project/programme formulation:
a) Liase
with donors and technical departments within MARD, and provide input in early
project design - in order to ensure co-ordination and that project contents
are in line with government policies.
b) Keep
a list of staff available from the different department that could participate
in planning teams and missions for donor funded projects.
3.
Information on on-going and pipe-line projects/programmes:
| First
| 2 | 3
| 4 | 5
| 6 | 7
| 8 | 9
| Last |
|